logo
香港 icon
icon 香港 icon
新闻与资讯
The Buildings Department inspected the Parkland I site
The Buildings Department inspected the Parkland I site 香港
By   Internet
  • 都市报
  • Parklon I land
  • property construction
  • new property projects
  • real estate
Abstract: MTR Kam Sheung Road Station Parklon I was allegedly not constructed in accordance with the plans, the Buildings Department said it had not received any notification from the developer before receiving media inquiries.

The Department sent officers to inspect the situation, and quoted the structural engineer of Parklon, because it does not constitute an immediate danger, so there is no report.

 

The developer reiterated yesterday that it attaches great importance to the quality of the project, and the implementation of the existing strict quality management system, the overall project progress and the structural safety and quality of the building will not be affected.

 

The Buildings Department said that according to the "Code of Practice for Site Supervision", if the registered building professionals, registered contractors and their qualified technical personnel found to be defective during the project, the relevant procedures must be initiated and corrected in accordance with the established mechanism, and if it poses an immediate danger, it must be reported to the Department of Building Services Supervision.

 

According to the Department, the registered structural engineer involved in the incident did not think the incident would pose an immediate danger and therefore did not report to the Buildings Department.

 

The Department also said that the registered structural engineer detected the error and subsequently corrected the project, showing that the existing regulatory and supervisory system to play an effective role.

 

The consortium of three developers to form the macro key limited yesterday, said the project site is now in the basement construction stage.

 

The supervisory team conducted a routine inspection earlier and found that there were discrepancies between the installation process of some columns and the approved plans, and immediately requested the main contractor to conduct a comprehensive inspection and follow-up, including the revision of the plan at the relevant locations to ensure compliance with all relevant regulations.

 

The plan has been agreed and confirmed by the Registered Structural Engineer and the rectification works are now in progress.

 

During the construction period, the team has put in place protective measures against dust and noise.

 

Wang Key reiterates that the overall project schedule and the structural safety and quality of the building will not be affected.

 

The site has just completed its foundation work, but it was revealed that some of the pillars were installed with wrong reinforcement.

 

The developer responded that during a routine inspection in mid-October, it was found that there were discrepancies between some of the column reinforcement tying processes and the approved plans, and that it had immediately instructed the main contractor to conduct a full inspection and make corrections to ensure that all structures met the requirements of the relevant regulations.

 

The corrections did not involve the demolition of any existing buildings.

留言
icon
请输入您的国籍
+87
不能为空
电子邮件地址无效 电子邮件地址未验证!
icon
欢迎访问 House.com
登录或注册以充分利用您的体验。这也将增加您与经纪人交流的机会。
请输入有效的电子邮件地址。
继续使用 Google
提交即表示我接受House.com的   使用条款
icon icon
验证您的电子邮件
你好 我们刚刚将验证码发送到您的电子邮件中。请检查并在此处输入验证码以继续登录。
验证码错误
没有收到电子邮件?请检查您的垃圾邮件文件夹
icon
banner
The Buildings Department inspected the Parkland I site
icon 复制链接
icon WhatsApp
icon Facebook
icon Twitter